Water Committee
Meeting Minutes
January 23, 2002
Present:
Jim Davis
Will Potter
Mike Shelton
Harriet Vaugeois
John Woods
|
Guest:
Bill Wenstrom
|
- Clyde Young Company had expected to have the
engineering study completed by this meeting, but due to an emergency on
another project, was unable to complete it. They received the information
needed from Vern Jaschke and also information from the manufacturer of the
pump station components. Clyde's preliminary, verbal report is that outside of
a few questions concerning the placement of some valves and not knowing if the
pumps will function automatically, everything else seems to look pretty good.
- Vern Jaschke has completed his analysis of the OPEC position and is
forwarding his comments to atttorney Robert Winter. Vern is also nearing
completion of the application to register our water system with the State of
Colorado and awaits the Clyde Young report for incorporation in the
filing.
- The other former and current committee members have or are completing
their respective responses to the OPEC position letter and are forwarding them
to attorney Robert Winter.
- John Woods reported that he is having difficulty getting the appropriate
information from Bill Quigley's files to complete the reconciliation of the
invoices from and payments to OPEC, as requested by the bonding company. Bill
Wenstrom related that there are additional Metro District records in Quigley's
office located in different files. John will get together again with the
Quigley staff.
- John Mitchell suggested that we draft the assignment agreement for the
power account fund balance ourselves, using the original transfer agreement
for the telephone and water account funds as the model. He will then review
and we will save some attorney fees. Jim Davis will do the draft.
- The question was
asked as to how soon we can get a new contractor started
after the Clyde Young report is completed. The contractor Clyde has recommended will be able to
begin as soon as he is notified of our desire to engage him. However,
the bonding company has requested sufficient time to review the engineering
report and our response to OPEC's position before we sign a new
construction contract. We feel that two weeks should give them sufficient time to
perform or be sued.
- The next committee meeting will be Wednesday, February 13, at 4pm at the Davis home.